|
Engine
Development
The primary propulsion
systems being designed for the JSF Program are derivatives of the F119-PW-100
engine that powers the F-22 Raptor. The propulsion system concepts for
both Weapon System Contractors (WSCs) use a P&W F119 core (compressor,
combustor and high pressure turbine). The F119, a low-bypass ratio turbofan,
is in the 35,000 lb-thrust class. The propulsion system concepts for the
Boeing and Lockheed Martin configurations utilize new fan and low-pressure
turbine (LPT) designs, which are based on F119 designs, materials and
processes. The JSF119 engines were based on the F119 for commonality and
cost reduction issues. These F119-derivative engines are in the 40,000
lb-thrust class. For the demonstrator program, both concepts take advantage
of F119 controls and externals as much as practical, but each aircraft
will use new nozzles.
 |
|
P&W
JSF119 engine and relationship to the F-22/F119
|
P&W began the CDP by completing
the preliminary design of the two selected engines, the JSF119-PW-614
for Boeing and the JSF119-PW-611 for Lockheed Martin. P&W then began extensive
facility modifications, altering test stands for carrier (CV) and conventional
take-off and landing (CTOL) engines as well as for STOVL tests of the
full-up propulsion systems (i.e., with the Roll-Royce (RR) and/or Rolls-Royce
Allison lift components), at P&W's West Palm Beach, Florida plant. These
facility modifications resulted in a total of four test stands for CV/CTOL
tests and one for STOVL operations as well as two tests stands for STOVL
operation with multi-component thrust measurement systems. Facility modifications
were also required at the Air Force's altitude test facilities at the
Arnold Engineering Development Center (AEDC) in Tullahoma, Tennessee,
to accommodate the JSF119 engines, since even the CV/CTOL versions are
much different than the F-22/F119 engine.
 |
|
|
JSF119 engine fabrication
began in March 1997 with the machining of the titanium billet that would
become the first stage fan integrally bladed rotor (IBR). Engine assembly
began when the first JSF compressor section was completed on 19 September
1997. The first JSF core was completed on 28 January 1998 at P&W's manufacturing
plant in Middletown, Connecticut.
The engine test program
is designed to clear the engines for flight in the shortest amount of
time as possible. P&W is building two developmental engines, two qualification
engines and two flight-test engines for the Boeing JSF design, and a similar
program for Lockheed Martin, with well over 1000 hours of ground test
time for each WSC. Engine testing began on 11 June 1998 with the commencement
of testing on the Lockheed Martin SE611; this was followed 10 days later
with the Boeing SE614. Although two months behind the extremely aggressive
contract goal date, the two engine designs were brought to test within
18 months of contract award through close coordination between the WSCs,
P&W, and their vendors.
 |
|
Boeing
STOVL engine with 2D nozzle on test stand at P&W. The large sieve-like
device and the long duct on the front of the engine serve as protection
from the ingestion of foreign objects.
|
These initial tests were
conducted at P&W's West Palm Beach facility and included component performance
evaluations, compression system stability demonstrations, vibration surveys,
operating system functional verification, and control software verification.
The JSF119 engines were then instrumented for simulated altitude testing
at AEDC. In over 120 hours of combined initial testing, the Boeing JSF119-614
and Lockheed Martin JSF119-611 engines demonstrated component efficiencies
higher than anticipated, turbine temperatures lower than predicted, and
very low vibration levels.
 |
|
Lockheed
Martin STOVL engine and Lift Fan undergoing testing. The bottom
of the Lift Fan is visible between the two engine intake ducts,
and discharges into exhaust ducting.
|
The STOVL engines began
testing in mid-November 1998 on P&W's unique test stands that have been
designed to measure forces in all directions to properly characterize
STOVL engine operation and its relationship with the aircraft vehicle
management system. By the end of 1998, P&W had four JSF119 engines under
test, having accumulated a total of approximately 200 hours. Testing has
continued with approximately 2000 hours of combined ground testing completed
as of early 2000.
|